Replacement of a powder coating booth in a 10-day shutdown

WAGNER SuperCenter EVO powder coating booth and powder centre, replaced during the production shutdown.
May 26, 2025 by
Replacement of a powder coating booth in a 10-day shutdown
SITE REFERENCEThe WAGNER SuperCenter EVO powder centre in operation.

Replacing a powder coating booth in 10 days of shutdown

Industry · 2025

WAGNER SuperCenter EVO powder coating booth and powder centre · Dismantling of the old booth, reassembly of the new one, participation in commissioning

Ten days. Not one more. At an industrial company, the old powder coating booth had to make way for a new one, and everything had to happen during the production shutdown. Dismantling, removal, reassembly, then taking part in the commissioning: ten consecutive days, from the first bolt removed to the restart of the line.

On this type of project, there is no catching up. The schedule is built upstream, to the hour, and is kept on site. It is an exercise that few companies agree to take on end to end: it commits as much on method as on the ability to mobilise a full team over a short window.

What we did

1
Preparation
Removal method, logistics of the elements and hour-by-hour schedule over the shutdown window.
2
Dismantling
Removal of the old booth and evacuation of the elements, as soon as the line stopped.
3
Reassembly
Assembly of the new booth, electrical and pneumatic connections.
4
Commissioning
Participation in settings and trials, up to the restart of production.

The result

✓ Old booth removed and new booth reassembled in ten consecutive days.
✓ A project kept within the customer's shutdown window, with no overrun.
✓ Production restarted within the announced deadline.

In pictures

Removing the old booth: the panels are dismantled and taken away by forklift.
The old booth dismantled, ready to be taken out of the workshop.
The area cleared, cleaned and prepared for the new booth.
Crane lifting of a module of the new booth.
The new booth reassembled on the line.
The WAGNER SuperCenter EVO powder centre in operation.

Thank you to the teams on site for their preparation and availability throughout the shutdown.

A line project, a retrofit or a part to find: use the contact form or call +33 4 38 61 25 77.

Jérôme Gautier, Managing Director, CREDO ENGINEERING FRANCE