A new powder coating booth in a three-week shutdown

Agricultural equipment manufacturer · Rhône (69). Dismantling of the old booth, assembly of the booth, cyclone, robot and powder centre, trials carried out with SAMES.
August 20, 2025 by
A new powder coating booth in a three-week shutdown
SITE REFERENCE

A new powder coating booth in a three-week shutdown

Agricultural equipment manufacturer · Rhône (69), Auvergne-Rhône-Alpes

Dismantling of the old booth · Booth, cyclone, robot and powder centre · Trials carried out with SAMES

Three weeks. That is the summer shutdown window we had to completely replace the powder coating booth of an agricultural equipment manufacturer in the Rhône: dismantle the old one, reassemble the new one and commission it.

A project of this size cannot be caught up. The dismantling of the old installation, the unloading of the new one and the assembly have to follow one another without downtime, and the application trials have to be done before the return to production. They were carried out on site with the SAMES teams, manufacturer of the application equipment.

What we did

1
Dismantling
Removal and evacuation of the old booth and its filter unit, workshop cleared for assembly.
2
Unloading and assembly
Unloading of the elements, crane reserved for lifting the stacks, then assembly of the booth, filters, ducts, cyclone, robot and powder centre.
3
Connections
Electrical and fluid connections, input and output tests, checks before power-up.
4
Trials and commissioning
Application settings and trials on parts, carried out with the SAMES teams, before the return to production.

The result

✓ A booth entirely replaced within the summer shutdown window. ✓ Application trials validated with the equipment manufacturer. ✓ A line restarted on the planned date.

In pictures

Dismantling and evacuation of the old booth and its filter unit.
Crane lifting of the stacks.
Application trials in the new booth.
Part being powder coated during the trials.
The new booth, access and platform in place.
The booth integrated into the existing line.
The SAMES powder centre and its control panel.

Thank you to the customer and to the SAMES teams for their trust and for the coordination of this shutdown window.

A line project, a retrofit or a part to find: use the contact form or call +33 4 38 61 25 77.

Jérôme Gautier, Managing Director, CREDO ENGINEERING FRANCE

Fast colour change at SMM
Chair manufacturer · Deux-Sèvres (79), 2023. WAGNER Flexi Center powder coating booth and powder centre, assembled during the Christmas shutdown.